Back to all tools
RCC Planning

Dhalan Cost Calculator Nepal

Plan an RCC slab casting day with concrete quantity, delivery loads, crew wages, equipment hire, site logistics, contingency, and cost per square foot.

WhatsApp

Slab and concrete

Use the structural drawing for slab area and thickness.

 

 

 

 

 

Casting-day resources

 

 

 

 

 

 

Concrete to order
12.389 m3
11.799 m3 net
Delivery loads
3
6.000 m3 each
Casting-day total
NPR 2,41,555
NPR 242 per ft2
Converted slab area
92.90 m2
ConcreteNPR 1,61,052
Crew wagesNPR 27,000
Equipment hireNPR 30,000
Site logisticsNPR 12,000
ContingencyNPR 11,503

How this works

Slab area and thickness determine the net wet concrete volume. The order quantity adds a handling allowance, then the planner combines concrete, one-day labour, equipment, logistics, and contingency.

net volume = area(ft2) x 0.092903 x thickness(in) x 0.0254
order volume = net volume x (1 + wastage%)
loads = ceil(order volume / load capacity)
total = (concrete + labour + equipment + logistics) x (1 + contingency%)

Reinforcement, shuttering, curing, and structural design are separate unless your entered rates expressly include them.

Worked example

A 1,000 ft2 slab at 5 in thickness needs about 11.79 m3 net concrete. With 5% allowance, order about 12.38 m3, or three 6 m3 delivery loads after checking the supplier's dispatch and minimum-order rules.

Sources

  • Quantity planning uses geometric wet volume; slab thickness and reinforcement must follow approved structural drawings.

FAQ

What is included in a dhalan day estimate?

This planner includes ordered concrete, one-day crew wages, pump or mixer hire, vibrator hire, site logistics, and contingency. Reinforcement and shuttering materials should be budgeted separately unless already contracted.

How much extra concrete should I order?

A small allowance is normally added for uneven shuttering, handling loss, pump residue, and measurement differences. The suitable percentage depends on site control and the supplier's minimum order.

Can I use this for site-mixed concrete?

Yes, but enter the combined per-cubic-metre cost of cement, sand, aggregate, and mixing. For detailed material quantities, use the concrete mix calculator as a cross-check.

Does the calculator design the slab thickness?

No. Slab thickness and reinforcement must come from structural drawings prepared or reviewed by a qualified engineer. This calculator only plans quantity, logistics, and casting-day cost.

What should be checked before casting starts?

Confirm reinforcement, cover blocks, sleeves, electrical conduits, shuttering line and level, access, backup equipment, labour, water, curing materials, cube tests, and weather arrangements.